Weston 7 Secondary Plan Project Updates

The Weston 7 Secondary Plan is nearing completion. The Plan is in phase 3, which includes navigating the secondary plan through the approvals process, a statutory public meeting, a recommendation report to the Committee of the Whole and Council adoption.

Image
A timeline of the Weston 7 Secondary Plan process. The Weston 7 Secondary Plan is in Phase 2 of the project.

 

What's Been Done To-date

The following work has been completed on the Weston 7 Secondary Plan and is available for public review:

 

Phase one: Background

The City of Vaughan retained a consulting team, led by Urban Strategies Inc., supported by HDR Inc., Hemson Consulting Ltd., The Municipal Infrastructure Group and Urban Equation, to undertake phase one of the Weston 7 Secondary Plan. Work began in May 2018 to identify the potential opportunities and constraints imposed by the study area's current conditions and external influences.

 

Phase one concluded with a final report presented at a Committee of the Whole Working Session on June 5, 2019. Review a summary of phase one work below:

 

Background report (Oct. 29, 2018)

Appendix 1: Transportation Needs Assessment Report

Appendix 2: Population and Employment Outlook and Commercial Use Assessment

Appendix 3: Sustainability Analysis

Appendix 4: Community Energy Plan

Appendix 5: Planning Policy Analysis

Appendix 6: Community Facilities and Services

Appendix 7: Preliminary Water Wastewater and Stormwater Servicing Analysis

Appendix 8: Telecommunications Memo

Committee of the Whole (Working Session): Report

Committee of the Whole (Working Session): Presentation

Final Report (May 10, 2019)

 

Phase two: Secondary plan development

Phase two of the Weston 7 Secondary Plan was initiated in May 2020 and led by a consulting team comprised of The Planning Partnership and supported by N. Barry Lyon Consultants, Arup, Urban Equation and Nbisiing Consulting. Phase two included the preparation of a draft Secondary Plan which provides a policy framework for land uses and built form, parks and open space, supporting transportation system and servicing to support the anticipated growth and creation of a complete community in Weston 7. Review a summary of phase two work below:

 

Background Report (April 21, 2021)

Weston 7 Secondary Plan Draft #1 (August 2023)

Committee of the Whole (Public Meeting) - November 1, 2023: Notice I Report I Presentation

Weston 7 Secondary Plan Draft #2 (October 2023)

Weston 7 Secondary Plan Draft #3 (May 2024)

Committee of the Whole (Working Session) - June 5, 2024: Notice I Report I Presentation

Committee of the Whole (2) - September 17, 2024: Staff Communication

Weston 7 Secondary Plan Draft #4 (November 2024)

Weston 7 Secondary Plan Draft #5 (May 2025)

 

Phase three: Approval

Building on phases one and two, phase three continues to seek feedback from the community, landowner groups and other interested stakeholders, as part of finalizing the Weston 7 Secondary Plan. During this phase, a final secondary plan will be presented to Council for a decision, providing a recommendation to guide future growth and development of the Weston 7 Secondary Plan study area into a complete, vibrant and active community. Review a summary of phase three work below:

 

Committee of the Whole (Public Meeting) - June 4, 2025: Notice I Report

Proposed New Weston 7 Secondary Plan (September 2025)

Committee of the Whole (1) - September 30, 2025: Notice I Report

 

Other secondary plan resources

 

To view the development applications that have recently been submitted in the W7SP study area, please see PLANit Viewer.