Kleinburg Village Improvements
Kleinburg Village Improvements continue!
We’re working to improve Kleinburg Village – and construction will resume this spring to bring roadway and streetscaping enhancements, new cycle paths (outside the village core) and more to the area.
The City of Vaughan hosted a fourth Open House on Thursday, April 16, 2026, at the McMichael Canadian Art Collection. Click here to see the presentation.
Weekly Construction Update
August 31 to September 4
- Temporary road closure for asphalt paving on Islington Avenue between Major Mackenzie Drive and Kleinburg Public School (see notice below under Disruption Alert).
- Temporary road closure for asphalt paving on Islington Avenue from Nashville Road to Hwy 27. (see notice below under Disruption Alert).
- Boulevard paver construction from Stegman's Mill Road to Pennon Road, west side.
- Road, curb & bike path construction from Hwy 27 to Nashville Road, east and west side.
- Road and lay-by curbs and casting from Treelawn Boulevard to Nashville Road.
- Boulevard paver construction from Rushworth Crescent to Stegman's Mill Road, east side.
- Bike path construction from Rushworth Crescent to Stegman's Mill Road, east side.
Disruption Alert
Road and boulevard improvements along Islington Avenue in Kleinburg Village are progressing, with the road anticipated to be fully re-opened by Monday, Sept. 7. The next phase of work includes completing construction on Islington Avenue, between Nashville Road and Bell Court, and paving the road. To safely and efficiently complete the work, temporary lane and road closures are required according to the following schedule:
• Islington Avenue, from Bell Court to Nashville Road: Northbound Lane closure will remain in place until Monday, Sept. 7.
• Islington Avenue, from Major Mackenzie Drive to Kleinburg Public School (10391 Islington Ave.): Paving operations from Monday, Aug. 24 to Friday, Aug. 28, between 7 a.m. and 7 p.m.
• Islington Avenue, from Nashville Road to Highway 27: Paving operations from Monday, Aug. 31 to Friday, Sept. 4, between 7 a.m. and 7 p.m.
Detour signs will be in place to guide traffic in the area. Access to homes and businesses along Islington Avenue will not be impacted.
To view the disruption alert please click here.
Temporary Parking During Construction
Alternate temporary parking will be made available just north of 10565 Islington Avenue and south of Treelawn Boulevard, and at the Kleinburg Public School (10391 Islington Ave.) from 4 p.m. to 11 p.m. on weekdays and from 6 a.m. to 11 p.m. on weekends when the work begins.
North of 10565 Islington Avenue and south of Treelawn Boulevard
Kleinburg Public School (10391 Islington Ave.)
Want to receive updates on the Kleinburg Village Improvements project? Subscribe to the project mailing list to receive construction and timeline updates.
Frequently Asked Questions
Additional Resources
Newsletters
- August 2021 | Newsletter No. 1
- July 2024 | Newsletter No.2
- May 2026 | Newsletter No.3
- August 2026 | Notice | Update (PDF)
Open House Notices
Public Information Centre Notices