Kleinburg Village Improvements Project Updates

Construction for the Kleinburg Village Improvements Project has begun and is expected to be completed by summer 2026. 

Weekly construction updates

 

May 25 - 29

  • Removal of hardscape and curbs from Stegman's Mill Road to Pennon Road, west side.
  • Road works and restoration from Stegman's Mill Road to Pennon Road, west side.
  • Sidewalk construction at the intersections of Kellam Street and Islington Avenue and Stegman's Mill Road and Islington Avenue.
  • Installing curbs and road work from Stegman's Mill Road to Pennon Road, west side
  • Electrical pole base and conduit construction on Islington Avenue and Stegman’s Mill Road.
  • Interlock paver installation on Islington Avenue between Nashville Road and Pennon Road, west side.
  • Ditch regrading works and retaining wall construction at Islington Avenue and Major Mackenzie Drive, northwest corner.

 

May 19 - 22

  • Removal of hardscape from Stegman's Mill Road to Pennon Road, west side.
  • Installing curb and road works from Stegman's Mill Road to Pennon Road, west side.
  • Sidewalk construction at the intersections of Kellem Street and Islington Avenue and Stegman's Mill Road and Islington Avenue.
  • Contractor continuing construction works for the York Region Transit retaining wall. 
  • Ditch regrading works at Islington Avenue and Major Mackenzie Drive, northwest corner.

 

May 11 - 15

  • Removal of hardscape from Stegman's Mill Road to Pennon Road, west side.
  • Installing layby lane and curb works from Stegman's Mill Road to Pennon Road, west side.
  • Stegman's Mill Road intersection, west side, installation of sidewalks, driveways, curbs, layby parking, and planter boxes.
  • Contractor continuing works for the York Region Transit retaining wall.
  • Ditch regrading works at Islington Avenue and Major Mackenzie Drive northwest corner.

 

May 4 - 8

  • Removal of hardscape from Stegman's Mill Road to Pennon Road west side.
  • Installing layby lane and curb works from Stegman's Mill Road to Pennon Road west side.
  • Stegman's Mill Road intersection, sidewalk, driveways, and layby parking.
  • Contractor continuing works for the York Region Transit retaining wall.
  • Ditch regrading works at Islington Avenue and Major Mackenzie Drive, northwest corner.

 

April 13 - 17

  • Contractor completing removal of curbs and hardscape from Kellam Street to Stegman’s Mill Road intersection (west side of Islington Avenue).
    • Traffic control and temporary lane disruptions are in place during the work.
  • Contractor completing installation of sidewalks, driveways, and layby parking.
  • Contractor installing planter boxes on completed hardscape areas. 
  • Contractor completing removals and grading at southwest corner of Islington Avenue and Major Mackenzie Drive.
  • Contractor completing general cleanup and temporary road repairs.

 

April 7 - 10

  • Contractor removal of valve chambers and interlock restoration.
  • Silt fence repairs on Islington Avenue and Major Mackenzie Drive.
  • Ditch regrading and flow rectification Northwest of Major Mackenzie Drive.
  • Interlock and curb removal Stegman's Mill Road intersection west.

 

March 23 - 27

  • Contractor site remobilization and minor clean up.
  • Traffic control set up and signage installation.
  • Pothole repair.
  • Full remobilization and construction start-up March 30, 2026.

 

January 2 - March 2026

  • Electrical contractor onsite to repair damaged temporary street lighting pole on the corner of Stegman's Mill Road and Islington Avenue.
  • Contractor demobilization and clean up in preparation for winter shutdown.
  • Work will pause as of Wednesday, Dec. 24 and will resume in March or April 2026, weather permitting.

 

Community engagement

 

Open House #4 was held on Thursday, April 16, 2026, at the McMichael Canadian Art Collection. To view the presentation boards, click here

 

Open House #3 was held on Monday, March 24, 2025, at the Kleinburg Library (10341 Islington Ave.). To view the presentation boards, click here.

 

Open House #2 was held on Thursday, June 20, 2024, for residents to find out more about the scope of work, construction timelines, impacts and more. To view the presentation material please click here.

 

Open House #1 was held on Tuesday, September 26, 2023, for residents to hear more about the project, receive updates on construction timelines and impacts, view renderings of what’s coming and ask questions directly to the project team. View material from the Open House (PDF).

 

Past community consultation

On Thursday February 10, 2022, residents were invited to attend a Public Information Session to learn more about the project, view a map and timelines, and ask questions directly to the project team. View the Public Information Session presentation (PDF).

 

Additional opportunities for feedback were provided throughout the following projects related to the area: