Kleinburg Village Improvements Project Updates
Construction for the Kleinburg Village Improvements Project has begun and is expected to be completed by summer 2026.
Weekly construction updates
April 13 - 17
- Contractor completing removal of curbs and hardscape from Kellam Street to Stegman’s Mill Road intersection (west side of Islington Avenue).
- Traffic control and temporary lane disruptions are in place during the work.
- Contractor completing installation of sidewalks, driveways, and layby parking.
- Contractor installing planter boxes on completed hardscape areas.
- Contractor completing removals and grading at southwest corner of Islington Avenue and Major Mackenzie Drive.
- Contractor completing general cleanup and temporary road repairs.
April 7 - 10
- Contractor removal of valve chambers and interlock restoration.
- Silt fence repairs on Islington Avenue and Major Mackenzie Drive.
- Ditch regrading and flow rectification Northwest of Major Mackenzie Drive.
- Interlock and curb removal Stegman's Mill Road intersection west.
March 23 - 27
- Contractor site remobilization and minor clean up.
- Traffic control set up and signage installation.
- Pothole repair.
- Full remobilization and construction start-up March 30, 2026.
January 2 - March 2026
- Electrical contractor onsite to repair damaged temporary street lighting pole on the corner of Stegman's Mill Road and Islington Avenue.
- Contractor demobilization and clean up in preparation for winter shutdown.
- Work will pause as of Wednesday, Dec. 24 and will resume in March or April 2026, weather permitting.
Community engagement
Open House #4 was held on Thursday, April 16 at the McMichael Canadian Art Collection. To view the presentation boards, click here.
Open House #3 was held on Monday, March 24 at the Kleinburg Library (10341 Islington Ave.). To view the presentation boards, click here.
Open House #2 was held on Thursday, June 20th for residents to find out more about the scope of work, construction timelines, impacts and more. To view the presentation material please click here.
Open House #1 was held on Tuesday, Sept. 26 for residents to hear more about the project, receive updates on construction timelines and impacts, view renderings of what’s coming and ask questions directly to the project team. View material from the Open House (PDF).
Past community consultation
In 2022, residents were invited to attend a Public Information Session to learn more about the project, view a map and timelines, and ask questions directly to the project team. View the Public Information Session presentation (PDF).
Additional opportunities for feedback were provided throughout the following projects related to the area:
- Sept. 2019/June 2020: Kleinburg Parking Strategy
- April 2018: Village of Kleinburg – Islington Avenue Streetscape Phase 1 (PDF)
- June 2011: Village of Kleinburg – Islington Avenue Streetscape Master Plan (PDF)
- June 2003: Islington Avenue Land Use Study, Urban Design Guidelines (PDF)