Project Updates

Learn more about the Black Creek Renewal Project as it progresses!

Weekly Construction Update

 

April 6 2026 to April 17 2026

  • Contractor installed underground drain pipe at northeast corner of Jane St and Highway 7.
  • Guiderail repair and surface restoration will be carried out, weather pending.

January 5 - January 9, 2026: 

  • Borehole and monitoring well installation at Edgeley Pond.

December 22 - January 2:

  • Winter holiday shutdown at Edgeley Pond.

 December 15 -19: 

  • Temporary pond excavation and material hauling at Edgeley Pond
  • Borehole and monitoring well installation at Edgeley Pond.

December 1 -12:

  • Borehole and monitoring well installation at Edgeley Pond.
  • Temporary pond and channel diversion work at Edgeley Pond.

November 17 - 28:

  • Borehole and monitoring well installation at Edgeley Pond.
  • Tree removal and bush removal
  • Temporary pond and channel diversion work at Edgeley Pond