Project Updates
Learn more about the Black Creek Renewal Project as it progresses!
Weekly Construction Update
September 29 - October 13, 2026
- Contractor continues Edgeley Pond excavation to remove existing pond sediment and transport for offsite disposal.
- Contractor begins to dewater the north pond to prepare diversion channel realignment.
- Contractor continues to import fill material
- Contractor continues with the demolition of existing building at 7685 Jane Street
September 14 - September 28, 2026
- Contractor continues Edgeley Pond excavation to remove organic soils and transport for offsite disposal.
- Contractor continues to place fill material at the pond.
- Contractor begins to demolish the existing building at 7685 Jane Street
June 8 - June 22, 2026
- Contractor continues Edgeley Pond excavation to remove organic soils and transport for offsite disposal.
- Contractor continues to place fill material at the pond.
May 25 - June 5, 2026
- Contractor resumes Edgeley Pond excavation to remove organic soils and transport for offsite disposal.
- Contractor begins to place fill material at the pond.
April 6 - April 17, 2026
- Contractor installed underground drain pipe at northeast corner of Jane St and Highway 7.
- Guiderail repair and surface restoration will be carried out, weather pending.
January 5 - January 9, 2026:
- Borehole and monitoring well installation at Edgeley Pond.
December 22 - January 2:
- Winter holiday shutdown at Edgeley Pond.
December 15 -19:
- Temporary pond excavation and material hauling at Edgeley Pond
- Borehole and monitoring well installation at Edgeley Pond.
December 1 -12:
- Borehole and monitoring well installation at Edgeley Pond.
- Temporary pond and channel diversion work at Edgeley Pond.
November 17 - 28:
- Borehole and monitoring well installation at Edgeley Pond.
- Tree removal and bush removal
- Temporary pond and channel diversion work at Edgeley Pond