Project Updates
Learn more about the Black Creek Renewal Project as it progresses!
Weekly Construction Update
April 6 2026 to April 17 2026
- Contractor installed underground drain pipe at northeast corner of Jane St and Highway 7.
- Guiderail repair and surface restoration will be carried out, weather pending.
January 5 - January 9, 2026:
- Borehole and monitoring well installation at Edgeley Pond.
December 22 - January 2:
- Winter holiday shutdown at Edgeley Pond.
December 15 -19:
- Temporary pond excavation and material hauling at Edgeley Pond
- Borehole and monitoring well installation at Edgeley Pond.
December 1 -12:
- Borehole and monitoring well installation at Edgeley Pond.
- Temporary pond and channel diversion work at Edgeley Pond.
November 17 - 28:
- Borehole and monitoring well installation at Edgeley Pond.
- Tree removal and bush removal
- Temporary pond and channel diversion work at Edgeley Pond