Garnet A. Williams Community Centre Renovation Project Updates
Project timeline
- 2019: Design consultants retained, pre-design begins
- 2019: Preliminary design
- 2020: Detailed design - community engagement
- 2021-2022: Construction
- 2023: Community centre partially open!
- 2024: Pool remains closed for renovations
Construction Progress
March 2024
- Ongoing fire alarm system testing that may cause some disruption but will be kept to a minimum
- Pool fire alarm system rectification is ongoing
- Pool changerooms have been completed but will remain offline until pool is opened for public use
- Ongoing general construction deficiencies are being addressed
- Wayfinding signage installation is in progress
- Installation of exterior metal paneling is in progress
- New exterior Splash pad equipment has been installed. Inspection and testing to be performed in Spring
- New exterior exit stair and ramp is in progress
- Finished landscaping is scheduled for completion in Spring
Spring 2023 Construction Update
Construction Photos
New north entrance
Image
New north facade
Image
New west entrance
Image
New west entrance drop off
Image
New arena entrance
Image
New west entrance lobby
Image
Pool change rooms and fitness centre
Image
New arena lobby
Image
New flex programs room
Image
New main corridor
Image
New arena pad
Image
New York Hill Park changeroom
Image
New splashpad and pool patio
Image