Use the drop down arrow below to navigate through our site
Portage Parkway Widening and Easterly Extension to Creditstone Road
Study Process and Timeline - COMPLETE
ConsultationA key component of the study included consultation with interested stakeholders (public and agencies). Two Public Information Centres (PICs) were held to present the study, review the study scope and discuss issues related to the project including alternative solutions, alternative designs, evaluation criteria, and environmental impacts and mitigation measures.
Study ChronologyNotice of Study Commencement - issued on June 12, 2015
Notice of Public Information Centre 1 - issued on November 10, 2015- Click here to view the display boards
Notice of Public Information Centre 2 - issued on February 23, 2016
- Click here for Display Boards
- Click here for Preliminary Preferred Design
Report to Committee of the Whole - June 21, 2016
Preliminary Preferred Design and Technical Appendices